  • His figures are ridiculously optimistic for nuclear, $6000/kW and 6 year construction times.
    Flamanville-3 and Olkiluoto-3 were both 12 years over their 5 year construction schedules. They were supposed to cost €3.3B and €3B respectively for 1650MW. Flamanville is expected to end up somewhere over €20B (€12000/kW), and Olkiluoto is somewhere around €11B, only due to ‘not to exceed’ limits in the supply contracts.

    Hinkley Point C has gone from £16B to near enough £30B for 3200MW (£9400/kW)

    It was the same with Vogtle 3 & 4. The preliminary budget of $12B, was changed initially to $14B at the start of construction. It’s now somewhere around $30B and 7 years late. The two AP1000s have a combined output of 2200MW ($13000/kW).
    V.C.Summer 2 & 3 was a similar pair of AP1000s. Costs went from $9B to $23B when the project was cancelled mid-construction.

    Wind and solar are far faster to deploy, and typically on or near budget. The new, much cheaper redox flow batteries (100 MW/400 MWh for $266M Dalian, China) are capable of smoothing intermittency in areas without hydro, which can perform a similar function.

    Edit. I should add that as of 2021, the global average for onshore wind is roughly $1300/kW. Prices continue to fall as new designs are introduced.


  • Just like assuming a perfectly spherical cow, or a frictionless surface, you can completely ignore the economics, the massive cost and schedule overages to make nuclear work.

    Flamanville-3 in France started construction in 2007, was supposed to be operational in 2012 with a project budget of €3.3B. Construction is still ongoing, the in-service date is now sometime in 2024, and the budget has ballooned to €20B.

    Olkiluoto-3 is a similar EPR. Construction started in 2005, was supposed to be in-service in 2010, but finally came online late last year. Costs bloated from €3 to €11B.

    Hinkley Point C project is two EPRs. Construction started in 2017, it’s already running behind schedule, and the project costs have increased from £16B to somewhere approaching £30B. Start up has been pushed back to 2028 the last I’ve heard.

    It’s no different in the US, where the V.C. Summer (2 x AP1000) reactor project was cancelled while under construction after projections put the completed project at somewhere around $23B, up from an estimate of $9B.

    A similar set of AP1000s was built at Vogtle in Georgia. Unit 3 only recently came online, with unit 4 expected at the end of the year. Costs went from an initial estimate of $12B to somewhere over $30B.

    Note that design, site selection, regulatory approvals, and tendering aren’t included in the above. Those add between 5-10 years to the above schedules.



  • Very early on in my career in consulting engineering, I had an architect tee-off on me for changing the ceiling heights of the office space she’d designed.

    I’m electrical, all I was concerned with was circuiting her lights, that was it. I had documentation showing that I’d worked off of exactly the same ceiling heights she had sent me. Heights that she’d apparently changed somewhere along the line without informing the client, who was an international conglomerate, and notoriously picky to work for.

    That could have blown over, had she not berated me over email while CCing the client, my management and just about anyone else involved with the project. I made sure to “reply all” showing where the change had happened. She was replaced on the project the following week.

    After that I stuck to industrial projects, where the buildings were non-descript concrete and steel boxes with no architectural involvement.



  • Dad had an interesting career. Started as an office clerk for a railway with only high school education. Then he got into using an IBM 650 (IIRC) for doing freight rate calculations. How he managed that transition, I have no idea. He didn’t care for being cooped up all day flipping switches, dealing with punch cards and tapes.

    He switched to marketing and got on there very well and retired after 37 years as a regional director.

    He always has a book on the go, even now at 83. He has an eclectic pile of them that he kept, from Zane Grey to an early history of the Civil War written around 1870.


  • Back when I was in junior high in the early 1980s, I found a copy of Atlas Shrugged on my father’s bookshelf, and started reading it. I can’t remember how far I got into it, but I do remember thinking it was just awful in just about every way: story, writing, pacing, everything.

    I asked Dad about it, “Oh, that. It’s terrible, isn’t it?” A friend had given it to him. Neither one of us finished reading it and after that it ended up at a book reseller.
    On the plus side, he’d gone through his books and gave me James Clavell’s Shogun to read, which was an awesome novel.








  • Sir_Osis_of_Liver@kbin.socialtoMemes@lemmy.ml3 browsers
    link
    fedilink
    arrow-up
    1
    arrow-down
    1
    ·
    1 year ago

    There were a number of sites that FF choked on, so I just ended up using Edge. uBlock works with it, and that’s about all I need for extensions.

    Not sure how people decided that Google is more altruistic with data handling than Microsoft, but here we are, I guess.